Commenting is now closed.

Click on the map to change the street view. Street View may not appear if not available through Google Maps.

Coordinates: 27.462822, -80.398979
Project ID: 4383791
ADD LANES & RECONSTRUCT
Non-SIS
Lead Agency: MANAGED BY FDOT
From: N OF I-95 OVERPASS
To: N OF COMMERCIAL CIR
Length: 1.4

Extra Description:

2017 TPO PRIORITY #4 WIDENING 2 TO 4 LANES PD&E UNDER 230256-5

Phase Group: PRELIMINARY ENGINEERING, RIGHT OF WAY, CONSTRUCTION, ENVIRONMENTAL



Contract Class: 4

Item Segment: 1

SIS: No

Component Group: HIGHWAYS

Related Key: 2302561

LRTP: Page 6-5

Responsible Agency



Agency: MANAGED BY FDOT
Type of Work: 213

Funding

PhaseFund Code20192020202120222023Total
ROWDDR06,585,980310,15600 6,896,136
ROWDIH0106,090106,09000 212,180
ROWDS03,999,2361,963,50900 5,962,745
CSTDDR000017,976,644 17,976,644
CSTDIH0000396,144 396,144
ENVDDR00060,0000 60,000
10,691,3062,379,75560,00018,372,788Total: 31,503,849

Prior Year Cost: 4,319,440

Future Year Cost: 0

Total Project Cost: 57,669,131

LRTP: Page 6-5
Print (Portrait) Print (Landscape)